LILAMA 18 WITH REMARKABLE RESULTS IN THE PROJECT WITH HOLCIM VIETNAM

Published date: 13/06/2013

In early June, Lilama 18 has officially handed over the static-electric dust filter system of Hon Chong cement plant to Holcim Vietnam after 10 months of performance and they have been highly appreciated by Holcim Vietnam.

    In the 2013 overhaul period for boiler of Hon Chong cement plant (Kien Lương – Kien Giang), Lilama18 signed a contract with Holcim Vietnam to remove the static-electric dust filter and install new bag dust filter for Holcim Hon Chong cement plant within 19 days. As we know, the same work in a former project of Holcim Corp. was implemented in 25 days, a record at that time.

 

 

    Lilama 18 has finished all this work within 17.85 days. This safe and sooner fulfilment helps Holcim reduce their interrupted time of production. Holcim Vietnam has awarded 400 million dongs to the labourers implementing that work. Moreover, a reward “Excellent and safe Contractor in boiler overhauling period in 2013”  has been awarded to Lilama 18 by Holcim.

    At Holcim Hon Chong cement plant project, Lilama 18 participated in a lot of important items in which the thermal recovery system of the plant was inaugurated in the end of 2012 and the static-electric dust filter system has been handed over recently.